System of acquisition and maintenance skills of the personnel not employed by RFI that performs maintenance activities to the railway infrastructure

download del file SAMAC Contracting companies

download del file SAMAC Contracting companies TE DITTE

download del file SAMAC Contracting companies MDO DITTE

This procedure aims to define the system of acquisition and conservation of skills for personnel not employed by RFI that conducts work activities in the sector of Railway Maintenance System. In particular they are attached files related for TE DITTE which allows to become the figure of Director of Construction Sites in works of electrical traction and MDO DITTE which allows the personnel by contracting companies to drive the railway vehicles, where the railway traffic is interrupted.


Instruction for the protection of sites -   download file

The document contains information about the procedures to be used during processing at the seat rail in order to protect the safety of workers. Describes how to perform the work and tasks of the Head of the Organization of the Protection of Shipyards and Duties of the Executive Officer relating to the protection of the Yards.


General requirements for the maintenance of the central apparatus - download file

The document contains the instructions for the general maintenance of the central apparatus.


Instructions for operating systems with electrical interlock. Manual electrical interlock type FS. - download file

The system provides for manual electric block to split the rail into several sections of operand block in such a way that each section is occupied by only one train at a time. Each section is called Guardablocco attended by agents in charge of the operation of the equipment and block signals. To prevent a Guardablocco can leave through a particular section more than one train is applied to the binary signal downstream of the first class that the same maneuver a device occupation constituted by pedals or by track circuits directly connected to the instrument of correspondence maneuvered by agent.


Instructions for operating systems with electrical interlock. Electrical interlocking axle counters. Double-track lines trivialized - download del file

The system block axle counter (B.ca) shall ensure the spacing of trains by signal controlled or controlled by special equipment, operated by the trains themselves, that counting the axes of the train in two specific points ensure the freedom of the road . With implantation of the block axle counter, the lines or line sections are divided into sections of block bounded by signals. This statement applies to your use of the system of double-track lines trivialized.


Instructions for operating systems with electrical interlock. Electrical interlocking axle counters. Double-track lines not trivialized - download file

The system block axle counter (B.ca) shall ensure the spacing of trains by signal controlled or controlled by special equipment, operated by the trains themselves, that counting the axes of the train in two specific points ensure the freedom of the road . With implantation of the block axle counter, the lines or line sections are divided into sections of block bounded by signals. This statement applies to your use of the system of double-track lines not trivialized.

Last modified 18/11/2015 15:25:44 / Visited 1521 Times